Pre-application consultation and application submission

We have finalised design development, environmental and technical work and have consulted with the public and local stakeholders. A planning application has been submitted to Vale of Glamorgan Council, we will update this website as the application progresses.

supporting net zero targets

The proposal would support the Welsh Government target of 100% of electricity consumption being generated from renewable energy by 2035, ending our reliance on fossil fuels such as coal, oil and natural gas and replacing these with new low carbon energy sources minimising future climate change and its impacts.

The proposal could produce enough renewable electricity for up to 2,600 homes each year, and offset over 3,800 tonnes of Co2 per year.*

*Renewable UK Wind Energy Statistics adapted via Statista UK

About the proPOSAL

The site consists of four development areas totalling approximately 41 acres (11.7 hectares), with the area within the red line boundary being circa 42.7 acres (17.3 hectares). The development site is located to the east of the village of Treoes.

Site Location

Proposed Site Location Plan

Timeline

Pre-application advice

Spring 2022

Pre-application advice and screening request submitted to Vale of Glamorgan Council.

Surveys

Summer / Autumn 2023

Surveys and development of early scheme proposal.

Environmental Impact Assessment (EIA) screening requests

Autumn 2023

EIA screening request submitted to Vale of Glamorgan Council. The response confirmed an EIA is not required for the proposal.

Pre-application consultation

January 2024

Pre-application consultation with local communities and stakeholders commenced.

Planning application submission

October 2024

Application submitted to Vale of Glamorgan Council.

Construction

2027

Construction to commence.

Grid connection

2028

Connecting the project into the local distribution network